Landen Laar windfarm consists of two wind turbines of max 200 m heigh, with a power of 7MW per turbine.
The turbines are located next to the busy train rails that connects Leuven to Luik. The turbines will produce 35.500MWh.
wind turbines
MW
per year
Project timeline
-
2021 - 2022
Haalbaarheidsanalyse
-
2023-augustus 2025
Studies & Vergunningsdossier opmaken
-
3 september 2025
Omgevingsvergunning ingediend
-
Oktober 2025
Openbaar onderzoek - Infomarkt
-
Oktober tot december 2025
Adviezen inwinnen
-
Februari 2026
Beslissing van minister van Omgeving